How Long Should A Bathroom Remodel Take?

by Anne B. Robinson
768 views

Estimating the time it will take to get a bathroom remodeled is not easy and is at least 50 percent prone to error. Nevertheless, it is a crucial step that must be taken by anyone that is considering renovating their bathroom, especially in the case where you do not have access to many bathrooms and need the process to be completed as soon as possible.

After all, leaving a bathroom incapacitated is a constant major inconvenience. This article will present the average time to remodel a bathroom by dividing the entire process into several components.

Design – 1 to 4 weeks

Before the renovation process even begins, some preliminary steps need to be taken, such as the design you are looking for. Therefore, you must have a clear and definitive idea of what exactly you want from the remodel before you even hire a contractor. Once you are sure that you have the idea, you will need to discuss it with the contractor.

The contractor will need some time to measure out the space according to your idea and consider the features you will want to be included and the location of where they should be placed. Not only that, but these details will also assist the contractor with estimating how much the bathroom remodel will cost.

Acquiring raw materials – 1 to 8 weeks

Once you have finalized a design and reached common ground with your contractor regarding the price, you can begin ordering the required materials. However, there are some things to bear in mind.

For example, if you decide to order custom items such as tiles, water closets, and cabinets from overseas, this stage can take longer than usual. Try your best to find a local supplier that provides the highest quality of materials to save as much time as possible.

Construction – 2 to 5 weeks

This stage is further divided into different categories to look at how long each step can take in this process.

Demolition

The very first stage of construction is the demolition of the existing bathroom. In general, this process can take a day or two at most and includes site preparation and installing dust barriers to safeguard the rest of the house from any waste produced from the demolition.

Framing and plumbing

Once the old bathroom is demolished, the next step is to transform the space into the desired result by framing and backing before working on plumbing and electrical components. Installing the bathtub, showers, and ventilation system can take around 3 to 4 days for this stage to complete.

Installation of walls

Installation of the walls after the drywall and moisture resistant boards are placed near sensitive areas allows the tiles to be placed. This stage can take a good amount of time, ranging from 5 to 12 days.

Accessories and counters

After the tiles have been placed, the bathroom walls can be applied with prime and the first coat of paint. Next, the last bits of construction is completed, such as countertops, plumbing, and electrical fixtures, along with the final coats of paint on the walls. This stage typically takes around 10 to 12 days.

Conclusion

As the construction is completed after approximately 25 days, there is a final step before you can begin using the new bathroom. The contractor will need to test the plumbing and electrical features to ensure that everything operates perfectly before cleaning up the good work. In the unlikely event of a blockage, you can always contact professionals for Help With Blocked Drain pipe, or you can check the internet for DIY solutions.